The modern definition of frustration is provided by Lord Radcliffe in Davis Contractors v Fareham Urban District Council [1956] AC 696:

Frustration occurs whenever the law recognises that, without default of either party, a [...] because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract ... It was not this that I promised to do.

Answer
contractual obligation has become incapable of being performed

Tags
#contract #frustration #law
Question
The modern definition of frustration is provided by Lord Radcliffe in Davis Contractors v Fareham Urban District Council [1956] AC 696:

Frustration occurs whenever the law recognises that, without default of either party, a [...] because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract ... It was not this that I promised to do.

Answer
?

Tags
#contract #frustration #law
Question
The modern definition of frustration is provided by Lord Radcliffe in Davis Contractors v Fareham Urban District Council [1956] AC 696:

Frustration occurs whenever the law recognises that, without default of either party, a [...] because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract ... It was not this that I promised to do.

Answer
contractual obligation has become incapable of being performed
If you want to change selection, open original toplevel document below and click on "Move attachment"

Parent (intermediate) annotation

Open it
The modern definition of frustration is provided by Lord Radcliffe in Davis Contractors v Fareham Urban District Council [1956] AC 696: Frustration occurs whenever the law recognises that, without default of either party, a contractual obligation has become incapable of being performed because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract ... It was not this that I promise

Original toplevel document (pdf)

cannot see any pdfs

Summary

statusnot learnedmeasured difficulty37% [default]last interval [days]               
repetition number in this series0memorised on               scheduled repetition               
scheduled repetition interval               last repetition or drill

Details

No repetitions


Discussion

Do you want to join discussion? Click here to log in or create user.