Question
In Dick Kerr and Co v Metropolitan Water Board [1918] AC 119, contractors agreed to construct a reservoir in six years. The contract provided that, in the event of delay, 'whatsoever and howsoever occasioned', the contractors were to apply to the engineer for an extension of time. When the contractors were required by a government order to stop the work and sell their plant, it was held that the contract was frustrated because [...]. It was held that the clause was intended to cover only temporary difficulties and did not cover fundamental changes in the nature of the contract.
Answer
the delay clause was not intended to apply to such a fundamental change of circumstances

Tags
#contract #frustration #law
Question
In Dick Kerr and Co v Metropolitan Water Board [1918] AC 119, contractors agreed to construct a reservoir in six years. The contract provided that, in the event of delay, 'whatsoever and howsoever occasioned', the contractors were to apply to the engineer for an extension of time. When the contractors were required by a government order to stop the work and sell their plant, it was held that the contract was frustrated because [...]. It was held that the clause was intended to cover only temporary difficulties and did not cover fundamental changes in the nature of the contract.
Answer
?

Tags
#contract #frustration #law
Question
In Dick Kerr and Co v Metropolitan Water Board [1918] AC 119, contractors agreed to construct a reservoir in six years. The contract provided that, in the event of delay, 'whatsoever and howsoever occasioned', the contractors were to apply to the engineer for an extension of time. When the contractors were required by a government order to stop the work and sell their plant, it was held that the contract was frustrated because [...]. It was held that the clause was intended to cover only temporary difficulties and did not cover fundamental changes in the nature of the contract.
Answer
the delay clause was not intended to apply to such a fundamental change of circumstances
If you want to change selection, open original toplevel document below and click on "Move attachment"

Parent (intermediate) annotation

Open it
soever occasioned', the contractors were to apply to the engineer for an extension of time. When the contractors were required by a government order to stop the work and sell their plant, it was held that the contract was frustrated because <span>the delay clause was not intended to apply to such a fundamental change of circumstances. It was held that the clause was intended to cover only temporary difficulties and did not cover fundamental changes in the nature of the contract.<span><body><html>

Original toplevel document (pdf)

cannot see any pdfs

Summary

statusnot learnedmeasured difficulty37% [default]last interval [days]               
repetition number in this series0memorised on               scheduled repetition               
scheduled repetition interval               last repetition or drill

Details

No repetitions


Discussion

Do you want to join discussion? Click here to log in or create user.