Question
An alternative basis for the assessment of damages is the reliance measure. This measure allows [...].
Answer
the claimant to recover the (wasted) expenses that have been incurred in preparing for, or in part performance of, the contract

Tags
#contract #law #remedies
Question
An alternative basis for the assessment of damages is the reliance measure. This measure allows [...].
Answer
?

Tags
#contract #law #remedies
Question
An alternative basis for the assessment of damages is the reliance measure. This measure allows [...].
Answer
the claimant to recover the (wasted) expenses that have been incurred in preparing for, or in part performance of, the contract
If you want to change selection, open original toplevel document below and click on "Move attachment"

Parent (intermediate) annotation

Open it
An alternative basis for the assessment of damages is the reliance measure. This measure allows the claimant to recover the (wasted) expenses that have been incurred in preparing for, or in part performance of, the contract.

Original toplevel document (pdf)

cannot see any pdfs

Summary

statusnot learnedmeasured difficulty37% [default]last interval [days]               
repetition number in this series0memorised on               scheduled repetition               
scheduled repetition interval               last repetition or drill

Details

No repetitions


Discussion

Do you want to join discussion? Click here to log in or create user.