The usual method of calculating the expectation interest in contracts involving defective works (e.g. where a building is not built to the contract specification), is [...](Birse Construction Ltd v Eastern Telegraph Co Ltd [2004] EWHC 2512).
Answer
the cost of cure
Tags
#contract #law #remedies
Question
The usual method of calculating the expectation interest in contracts involving defective works (e.g. where a building is not built to the contract specification), is [...](Birse Construction Ltd v Eastern Telegraph Co Ltd [2004] EWHC 2512).
Answer
?
Tags
#contract #law #remedies
Question
The usual method of calculating the expectation interest in contracts involving defective works (e.g. where a building is not built to the contract specification), is [...](Birse Construction Ltd v Eastern Telegraph Co Ltd [2004] EWHC 2512).
Answer
the cost of cure
If you want to change selection, open original toplevel document below and click on "Move attachment"
Parent (intermediate) annotation
Open it The usual method of calculating the expectation interest in contracts involving defective works (e.g. where a building is not built to the contract specification), is the cost of cure (Birse Construction Ltd v Eastern Telegraph Co Ltd [2004] EWHC 2512).
Original toplevel document (pdf)
cannot see any pdfs
Summary
status
not learned
measured difficulty
37% [default]
last interval [days]
repetition number in this series
0
memorised on
scheduled repetition
scheduled repetition interval
last repetition or drill
Details
No repetitions
Discussion
Do you want to join discussion? Click here to log in or create user.