Question
In Hochster v De la Tour the defendant agreed to employ the plaintiff as a courier on foreign tours for a period of three months starting from 1 June. But on 11 May the defendant wrote and told the plaintiff that his services were no longer required. The plaintiff immediately sued the defendant. The defendant argued that the plaintiff should not succeed in his action unless he could show that he was ready and able to perform his obligations on 1 June. The court found in favour of the plaintiff. He had a choice as to [...].
Answer
whether to wait for the date of performance, in which case he would need to be ready to perform his obligations, or to treat the contract as immediately repudiated

Tags
#contract #discharge #law
Question
In Hochster v De la Tour the defendant agreed to employ the plaintiff as a courier on foreign tours for a period of three months starting from 1 June. But on 11 May the defendant wrote and told the plaintiff that his services were no longer required. The plaintiff immediately sued the defendant. The defendant argued that the plaintiff should not succeed in his action unless he could show that he was ready and able to perform his obligations on 1 June. The court found in favour of the plaintiff. He had a choice as to [...].
Answer
?

Tags
#contract #discharge #law
Question
In Hochster v De la Tour the defendant agreed to employ the plaintiff as a courier on foreign tours for a period of three months starting from 1 June. But on 11 May the defendant wrote and told the plaintiff that his services were no longer required. The plaintiff immediately sued the defendant. The defendant argued that the plaintiff should not succeed in his action unless he could show that he was ready and able to perform his obligations on 1 June. The court found in favour of the plaintiff. He had a choice as to [...].
Answer
whether to wait for the date of performance, in which case he would need to be ready to perform his obligations, or to treat the contract as immediately repudiated
If you want to change selection, open original toplevel document below and click on "Move attachment"

Parent (intermediate) annotation

Open it
the defendant. The defendant argued that the plaintiff should not succeed in his action unless he could show that he was ready and able to perform his obligations on 1 June. The court found in favour of the plaintiff. He had a choice as to <span>whether to wait for the date of performance, in which case he would need to be ready to perform his obligations, or to treat the contract as immediately repudiated.<span><body><html>

Original toplevel document (pdf)

cannot see any pdfs

Summary

statusnot learnedmeasured difficulty37% [default]last interval [days]               
repetition number in this series0memorised on               scheduled repetition               
scheduled repetition interval               last repetition or drill

Details

No repetitions


Discussion

Do you want to join discussion? Click here to log in or create user.