Do you want BuboFlash to help you learning these things? Or do you want to add or correct something? Click here to log in or create user.



Tags
#consideration #contract
Question
Facts: The plaintiff contracted to erect stands at Olympia for the defendant. A week before the exhibition the plaintiff’s workman went on strike, refusing to return to work until a pay demand was met. The plaintiff told the defendant that unless the defendant paid an additional £4,500 the contract would be cancelled. The plaintiff made it clear that the amount to be paid was to be in addition to the contract price. The defendant paid the amount demanded as the cancellation of the contract would have caused serious damage to the defendant's economic interests. At the end of the contract, the defendant deducted the £4,500 from the contract price. The plaintiff claimed the balance. It was held that the plaintiff had agreed to make the extra payment under duress.
Answer
B & S Contracts and Design Ltd v Victor Green Publications Ltd [1984] ICR 419

Tags
#consideration #contract
Question
Facts: The plaintiff contracted to erect stands at Olympia for the defendant. A week before the exhibition the plaintiff’s workman went on strike, refusing to return to work until a pay demand was met. The plaintiff told the defendant that unless the defendant paid an additional £4,500 the contract would be cancelled. The plaintiff made it clear that the amount to be paid was to be in addition to the contract price. The defendant paid the amount demanded as the cancellation of the contract would have caused serious damage to the defendant's economic interests. At the end of the contract, the defendant deducted the £4,500 from the contract price. The plaintiff claimed the balance. It was held that the plaintiff had agreed to make the extra payment under duress.
Answer
?

Tags
#consideration #contract
Question
Facts: The plaintiff contracted to erect stands at Olympia for the defendant. A week before the exhibition the plaintiff’s workman went on strike, refusing to return to work until a pay demand was met. The plaintiff told the defendant that unless the defendant paid an additional £4,500 the contract would be cancelled. The plaintiff made it clear that the amount to be paid was to be in addition to the contract price. The defendant paid the amount demanded as the cancellation of the contract would have caused serious damage to the defendant's economic interests. At the end of the contract, the defendant deducted the £4,500 from the contract price. The plaintiff claimed the balance. It was held that the plaintiff had agreed to make the extra payment under duress.
Answer
B & S Contracts and Design Ltd v Victor Green Publications Ltd [1984] ICR 419
If you want to change selection, open original toplevel document below and click on "Move attachment"

Parent (intermediate) annotation

Open it
B & S Contracts and Design Ltd v Victor Green Publications Ltd [1984] ICR 419 Facts: The plaintiff contracted to erect stands at Olympia for the defendant. A week before the exhibition the plaintiff’s workman went on strike, refusing to return to work until a pay

Original toplevel document (pdf)

cannot see any pdfs

Summary

statusnot learnedmeasured difficulty37% [default]last interval [days]               
repetition number in this series0memorised on               scheduled repetition               
scheduled repetition interval               last repetition or drill

Details

No repetitions


Discussion

Do you want to join discussion? Click here to log in or create user.