Do you want BuboFlash to help you learning these things? Or do you want to add or correct something? Click here to log in or create user.



Question

n = (l+m) / l

where:

n = Number of machines the operator is assigned

l = Total operator [...] time per machine

m = Total machine running time

Answer
loading and unloading

Question

n = (l+m) / l

where:

n = Number of machines the operator is assigned

l = Total operator [...] time per machine

m = Total machine running time

Answer
?

Question

n = (l+m) / l

where:

n = Number of machines the operator is assigned

l = Total operator [...] time per machine

m = Total machine running time

Answer
loading and unloading
If you want to change selection, open original toplevel document below and click on "Move attachment"

Parent (intermediate) annotation

Open it
n = (l+m) / l where: n = Number of machines the operator is assigned l = Total operator loading and unloading time per machine m = Total machine running time

Original toplevel document (pdf)

owner: orantisiz - (no access) - 4-activity_charts-23.pdf, p5

Summary

statusnot learnedmeasured difficulty37% [default]last interval [days]               
repetition number in this series0memorised on               scheduled repetition               
scheduled repetition interval               last repetition or drill

Details

No repetitions


Discussion

Do you want to join discussion? Click here to log in or create user.