n = (l+m) / l

where:

n = Number of machines the operator is assigned

l = Total operator loading and unloading time per machine

m = Total [...]

Answer
machine running time

Question

n = (l+m) / l

where:

n = Number of machines the operator is assigned

l = Total operator loading and unloading time per machine

m = Total [...]

Answer
?

Question

n = (l+m) / l

where:

n = Number of machines the operator is assigned

l = Total operator loading and unloading time per machine

m = Total [...]

Answer
machine running time
If you want to change selection, open original toplevel document below and click on "Move attachment"

Parent (intermediate) annotation

Open it
n = (l+m) / l where: n = Number of machines the operator is assigned l = Total operator loading and unloading time per machine m = Total machine running time

Original toplevel document (pdf)

owner: orantisiz - (no access) - 4-activity_charts-23.pdf, p5

Summary

statusnot learnedmeasured difficulty37% [default]last interval [days]               
repetition number in this series0memorised on               scheduled repetition               
scheduled repetition interval               last repetition or drill

Details

No repetitions


Discussion

Do you want to join discussion? Click here to log in or create user.